Although I'm working with FieldOne for a few months now I'm still pretty new to it. As of a week we are having our first case for a customer and I could use some help. I would like to create a dependency between tasks on a work order (I think) so that task B can only be executed when task A is completed. This is the situation: The customer gets a request to do adjustments to cables in the ground. Therefore a hole needs to be digged and the adjustments to the cables needs to be done. Logically the adjustments to the cable can only be done when there is a hole in the ground. Furthermore, the digging of the hole and the adjustments are done by different resources who are not on the same place on the same time. Would you create two workorder schedules for one workorder? And the follow up question would be how do you make sure that a Dispatcher can only plan task / workorder schedule B after A is plann ed. Thanks in advance
↧